Cherrydale Road, Ely, Cardiff
Groundworks & Civil’s work to deliver seven modular homes
Project Value – £1.04m
Main Contractor – Wates Residential
Commencement Date – Sept 24
Project Duration – 13 Months
Contract – JCT D&B 2018
Groundworks & Civil’s work to deliver seven modular homes
Project Value – £1.04m
Main Contractor – Wates Residential
Commencement Date – Sept 24
Project Duration – 13 Months
Contract – JCT D&B 2018
Land remediation, manage and deliver an all risk package comprising of Bulk Earthworks and Disposal of Surplus material in line with a CLAIRE Material Management Plan to ensure end use is safe, Provide Masonry Screen walls, Foundations, Substructure masonry, Adoptable Foul and Storm Drainage, SAB features and attenuation tanks, Main Services/utilities, Adoptable roads and Footpaths. Provide all temporary enabling works to allow transportation and placement of the modular units.