Gower College

Overview

Gower College, Gowerton, Swansea

All Associated Groundworks & Civils Package for a school Extension within a live school environment.

  • Project Value – £2.5m

  • Main Contractor – Kier Construction

  • Commencement Date – August 24

  • Project Duration – 20 Months

  • Contract – NEC Option A with Z clauses.

Require specialist groundworks and civil engineering to the very highest of standards?

Scope of Works

Bulk Earthworks, breaking out rock, disposal of Surplus Non-Hazardous soils off site, Japanese Knot weed eradication, cast insitu retaining walls, Amphitheatre Steps, Complex Mass poured foundation in a made ground environment, Structural foundation to facilitate a portal steel frame, Substructure masonry, Floors & Ground bearing floors, CS2 Gas membrane. Foul and Storm Drainage, Attenuation tanks, Rainwater Harvesting tanks, SAB features, Main Services/utilities, Soft and hard landscaping.

Start Your Project

If you’d like to discuss an upcoming project or view similar work we’ve completed, get in touch with our team today.

Designed & built by eInfinity Limited. Hosting & IT management at eInfinity Tech.